Sequence step algorithm for continuous resource utilization in probabilistic repetitive projects

Published: 03 December 2006 Publication History

Abstract

The sequence step algorithm addresses for the first time the problem of scheduling repetitive projects with probabilistic activity durations while maintaining continuous resource utilization. This algorithm is based on generalized concepts that can be implemented in most general-purpose simulation systems. The algorithm is presented in detail and is applied to an example project with 7 activities and 4 repetitive units using a simulation model developed in Stroboscope, an activity-based simulation system. Numerical and graphical results help explain the algorithm and provide insight into the underlying tradeoff problem between reducing the expected crew idle time and increasing the expected project duration.

References

[1]
Harris, R. B. 1978. Precedence and Arrow Networking Techniques for Construction. John Wiley & Sons, Inc., New York, ISBN 0-471-04123-8, 50--51.
[2]
Harris, R. B., and P. G. Ioannou. 1998. Scheduling projects with repeating activities. Journal of Construction Engineering and Management, ASCE, July/August 1998, 269--278.
[3]
Ioannou, P. G., and V. Likhitruangsilp. 2005. Simulation of multiple-drift tunnel construction with limited resources, In Proceedings of the 2005 Winter Simulation Conference, ed. M. E. Kuhl, N. M. Steiger, F. B. Armstrong, and J. A. Joines, 1483--1491. Piscataway, New Jersey: Institute of Electrical and Electronics Engineers.
[4]
Martinez, J. C. 1996. STROBOSCOPE: State and resource based simulation of construction processes. Doctoral Dissertation, Dept. of Civil and Environ. Engineering, University of Michigan, Ann Arbor, Michigan.
[5]
Martinez, J. C. and P. G. Ioannou. 1999. General Purpose Systems For Effective Construction Simulation. Journal of Construction Engineering and Management, ASCE, (125)4, July-August 1999.

Cited By

View all
  • (2009)Resource leveling of linear schedules with singularity functionsWinter Simulation Conference10.5555/1995456.1995806(2571-2582)Online publication date: 13-Dec-2009
  • (2008)Simulation and optimization for construction repetitive projects using promodel and SimRunnerProceedings of the 40th Conference on Winter Simulation10.5555/1516744.1517166(2402-2412)Online publication date: 7-Dec-2008
  • (2007)Optimal scheduling of probabilistic repetitive projects using completed unit and genetic algorithmsProceedings of the 39th conference on Winter simulation: 40 years! The best is yet to come10.5555/1351542.1351923(2151-2158)Online publication date: 9-Dec-2007
  • Show More Cited By

Recommendations

Comments

Information & Contributors

Information

Published In

cover image ACM Conferences
WSC '06: Proceedings of the 38th conference on Winter simulation
December 2006
2429 pages
ISBN:1424405017

Sponsors

  • IIE: Institute of Industrial Engineers
  • ASA: American Statistical Association
  • IEICE ESS: Institute of Electronics, Information and Communication Engineers, Engineering Sciences Society
  • IEEE-CS\DATC: The IEEE Computer Society
  • SIGSIM: ACM Special Interest Group on Simulation and Modeling
  • NIST: National Institute of Standards and Technology
  • (SCS): The Society for Modeling and Simulation International
  • INFORMS-CS: Institute for Operations Research and the Management Sciences-College on Simulation

Publisher

Winter Simulation Conference

Publication History

Published: 03 December 2006

Check for updates

Qualifiers

  • Article

Conference

WSC06
Sponsor:
  • IIE
  • ASA
  • IEICE ESS
  • IEEE-CS\DATC
  • SIGSIM
  • NIST
  • (SCS)
  • INFORMS-CS
WSC06: Winter Simulation Conference 2006
December 3 - 6, 2006
California, Monterey

Acceptance Rates

WSC '06 Paper Acceptance Rate 177 of 252 submissions, 70%;
Overall Acceptance Rate 3,413 of 5,075 submissions, 67%

Contributors

Other Metrics

Bibliometrics & Citations

Bibliometrics

Article Metrics

  • Downloads (Last 12 months)0
  • Downloads (Last 6 weeks)0
Reflects downloads up to 07 Mar 2025

Other Metrics

Citations

Cited By

View all
  • (2009)Resource leveling of linear schedules with singularity functionsWinter Simulation Conference10.5555/1995456.1995806(2571-2582)Online publication date: 13-Dec-2009
  • (2008)Simulation and optimization for construction repetitive projects using promodel and SimRunnerProceedings of the 40th Conference on Winter Simulation10.5555/1516744.1517166(2402-2412)Online publication date: 7-Dec-2008
  • (2007)Optimal scheduling of probabilistic repetitive projects using completed unit and genetic algorithmsProceedings of the 39th conference on Winter simulation: 40 years! The best is yet to come10.5555/1351542.1351923(2151-2158)Online publication date: 9-Dec-2007
  • (2007)Optimal work breaks in deterministic and probabilistic repetitive projectsProceedings of the 39th conference on Winter simulation: 40 years! The best is yet to come10.5555/1351542.1351922(2141-2150)Online publication date: 9-Dec-2007

View Options

Login options

View options

PDF

View or Download as a PDF file.

PDF

eReader

View online with eReader.

eReader

Figures

Tables

Media

Share

Share

Share this Publication link

Share on social media